Urology P.C. Additions and Renovations- Site and Foundation Package

Public bid opportunity

Urology P.C. Additions and Renovations- Site and Foundation Package

Bids Due
Sep 21, 2017 2:00pm
Work Begins
Oct 02, 2017
Expected Completion
Oct 19, 2018
Scope of Work

The project includes two additions and extensive interior cosmetic upgrade to existing medical clinic at the Urology Clinic located at 56th and Pine Lake Road.  The scope of the work for this initial bid package includes site preparation, site utilities, foundations, helical supports, structural steel materials, and site paving.  Work for this package is to proceed in early October.

Contact Information

Tim Donner
402-477-6745
Cheever Construction Company 3425 North 44th Street Lincoln, Nebraska 68504 Phone: 402.477.6745 Fax: 402.477.2063
Plan Review Available at